  • Installation of Process Water Systems – JLR Engine Plant Wolverhampton – May 2013
  • Installation of 10 off basecoats, 2 Primers, 1 Clearcoats, solvents and solvent reclaims - FMC Valencia – April 2013
  • Installation of Phosphate Cyclones – JLR Halewood – March 2013
  • Installation of 204 Anodes on the Electrocoat System – JLR Solihull – February 2013
  • Installation of Chilled Water Systems – JLR Halewood – December 2012
  • Installation of 2 off main line basecoat systems, mix room and 4 off mini basecoat systems – Rolls Royce Chichester – October 2012
  • Installation of Ram Units and High Pressure Systems – Toyota Burnaston – September 2012
  • Installation of Wax Pumping / Application System – Nissan Sunderland – August 2012
  • Installation of Bumper Plant paint circulation systems – Nissan Sunderland – July 2012
  • Installation of Dust Tunnels – JLR Solihull – July 2012
  • Installation of Bulk Sealer Systems – GM Luton – July 2012
  • Installation of 2 off ‘Easy Clean’ Basecoat Systems – GM Luton – May 2012
  • Installation of 2 off Spot Repair Booths and Paint Mix Room – JLR Halewood – April 2012
  • Installation of Solvent Recovery Systems – BMW Oxford – February 2012
  • Installation of Various Process Pipework Systems – Airbus Broughton – 2012 to 2013
  • Installation of Scissor Lifts – JLR Halewood – January 2012
  • Installation of 60,000 Litre Diesel Tank – Caterpillar Desford – December 2011
  • Installation of 7 off ‘Easy Clean’ Paint Mix and Distribution Systems – JLR Solihull – November 2011
  • Installation of Tinted Clearcoat Systems and Robot 2K Application Systems – FMC Genk – September 2011
  • Upgrade of Paint Application Robots and Machines – JLR Solihull – July 2011
  • Installation of 10 off ‘Easy Clean’ and 2K Paint Systems – Mclaren Automotive – May 2011
  • Installation of Waste Water Treatment Plants – Kurion Technologies – April 2011
  • Installation of Ram Units and High Pressure Systems – Toyota France – March 2011
  • Manufacture and Installation of Pre Treatment / Electrocoat Systems – Metokote Germany – January 2011